What is a QPR (Quarterly Progress Report)?
The Quarterly Progress Report (QPR) is a mandatory filing under the RERA Act requiring registered real estate developers to report project progress every quarter on the MahaRERA portal. It covers construction completion percentage, unit sales, financial status, and escrow account position.
Failure to file accurately and on time exposes developers to penalties under §63 of the RERA Act — up to 5% of the estimated project cost per quarter.
MahaRERA QPR Deadlines 2026
| Quarter | Period | Deadline | Status |
|---|
| Q4 2025-26 | Jan–Mar 2026 | July 15, 2026 | ⚠️ Approaching — file now |
| Q1 2026-27 | Apr–Jun 2026 | July 15, 2026 | Scheduled |
| Q2 2026-27 | Jul–Sep 2026 | October 15, 2026 | Scheduled |
| Q3 2026-27 | Oct–Dec 2026 | January 15, 2027 | Scheduled |
July 15, 2026 deadline is approaching. If you are not already filing, start immediately. ReraDesk sends automated alerts at 30, 14, and 7 days before each deadline.
Penalty for missing QPR deadlines
Under §63 of the RERA Act, non-compliance with RERA authority orders — including QPR filing requirements — can attract:
- Up to 5% of estimated project cost per quarter for QPR non-compliance
- On a ₹10 crore project: ₹50 lakh per quarter, compounding every 3 months
- MahaRERA authority escalation for repeat non-filers including project de-registration risk
- Promoter personal liability — not just the company
Penalty amounts are subject to MahaRERA discretion. Consult a qualified RERA advocate for your specific situation.
QPR Filing Checklist
- Construction completion certificate from registered architect (Form 1)
- Structural engineer certificate (Form 2) where applicable
- Escrow bank statement showing 70% balance maintenance
- Unit sales register: units sold, booked, available, handed over
- CA-certified financial figures (Form 3 if escrow withdrawal)
- Updated site photographs — mandatory per quarter in most states
- Any change in project details vs. previous quarter
How to file on the MahaRERA portal
- Login at maharera.maharashtra.gov.in ↗
- Navigate to your project → Quarterly Update
- Fill all mandatory fields: completion %, financial data, unit status
- Upload required supporting documents
- Get CA review and certification for financial figures
- Submit and download the acknowledgment receipt